2023 年质量管理经验交流论文汇编
提高山地光伏高桩组件安装效率研究
晏波,刘远望,刘诗泽
中国电建江西省电力设计院有限公司,江西省南昌市,330000
摘要:本文通过对高桩组件安装效率,开展 QC 小组活动,确定了导致山地光伏
高桩组件安装效率低的主要原:安装组件人员经验不足、安装作业平台选择不合
理、施工方案没有针对性、组件分运不合理等,进而制定针对性措施解决了高桩
组件安装效率低的问题。
关键字:林光互补;光伏组件安装
Research on improving the installation efficiency of
photovoltaic high-pile modules in mountainous areas
Yan Bo,Liu Yuanwang,Liu Shize
PowerChina Jiangxi Electric Power Engineering Co., Ltd.Nanchang city,Jiangxi Province
Abstract: Through carrying out QC group activities on the installation efficiency of high pile
modules, this paper identified that the main reasons for the low efficiency of installation of high
pile modules in mountain areas were the lack of experience of the installation personnel, the
unreasonable selection of the installation operation platform, the lack of pertinence of the
construction scheme, and the unreasonable distribution of components, and then formulated
targeted measures to solve the problem of low efficiency of installation of high pile modules.
Key words: Complementary photovoltaic advantages of forest land;PV module installation
1 前言
山地光伏项目地表海拔高差较大,山脚因长期积水土质松软,同时因需考虑洪水位问题,
管桩长度往往较长(管桩露出地面高度一般在 2 米以上,此类管桩本文简称高桩)。高桩组
件安装采用移动式脚手架踏板施工因地面硬度不足,安全性系数不高,采用搭通长脚手架,
耗时又浪费成本。
光伏项目短、平、快,如何在保证安装质量、安全的前提下,提高高桩组件安装进度,
满足工程并网节点要求,是山地光伏一大难点。针对上述问题,本课题小组就此问题开展
QC 活动。
2 工程情况
工程位于国内某电厂的事故灰场,光伏组件的安装倾角为 12°,坡地积水严重,淤泥
质土平均深度在 3 米左右,坡地管桩设计长度为 9m-12m,组件安装平台搭设难度大,高桩
组件安装进度缓慢,无法满足既定工期要求。
2.1 工程安装
2.1.1 现状调查
本工程总装机容量 22MW,分为 5 个阵列,每个阵列 4.4MW 组件,阵列 1 高桩 40 组,阵
列 2 高桩 42 组,阵列 3 高桩 25 组,共计 107 组。
阵列 1 高桩组件安装时,先利用现场光伏支架中的檩条做支撑,此种方式虽成本低廉,
但极易造成檩条的损坏,同时与支架厂家沟通确认,檩条设计强度未考虑承载安装工人重量。
后改为移动式脚手架,移动式脚手架在安装高度在 2.5 米以下的管桩时,施工便捷成本
低廉,但受限于山地光伏地表崎岖不平,移动脚手架一般搭设高度都在 2 米以内,过高容易
失稳侧翻,无法满足高桩组件安装需求。
为满足高桩组件安装需求,阵列1的40组高桩采用搭设固定式钢管架的方式进行安装,
安全系数高,同时可根据管桩高度灵活调整钢管架搭设高度,满足不同高度的高桩组件安装
需要。但搭设一组高桩组件及后续拆除时间较长,无形增加了组件的安装时长,同时也增加
了管架的搭设及拆卸成本。
204